Still One Year To Go 

Busy spring ahead as work on Jnct 16 continues
 
Around 100,000 tonnes of clay will be transported onto Junction 16 of the M4 over the coming months as part of the latest phase of works to transform the key highway interchange.

A dozen lorries this week began transporting the clay on to the site to raise several areas next to the current carriageway in order to provide the additional road surface required for the new junction layout.

The lorries will be dropping off the clay between 8am and 5.30pm and will be travelling between Brinkworth and the motorway junction on a regular basis throughout the day. This is expected to continue until July.

Jn16, M4 Swindon
Completion in spring 2018:
Jn16, M4 Swindon
 
Approximately 2,000 tonnes of material will be transported each day, with the total quantity of imported clay being approximately 100,000 tonnes.

It is anticipated this phase of the work will have a minimal impact on traffic, but the situation will be monitored. A road sweeper will operate throughout the day to ensure the road is kept as clear as possible and the lorries will enter and exit the site via established works access points. No lane closures will be allowed during peak hours.

The £11.5m upgrade of Junction 16 will ensure it can cope with forecast future traffic levels and cater for future development in the surrounding areas, including the nearby Wichelstowe development which will see thousands of new homes built over the next few years.

The improvements are being funded by Swindon and Wiltshire Local Enterprise Partnership and Swindon Borough Council as part of the Wichelstowe development. It is being delivered by Swindon Borough Council in partnership with Highways England and Wiltshire Council.
 
Jn16, M4 Swindon
 
The contractor, HOCHTIEF (UK) Construction Ltd, is on track to complete the scheme by spring 2018. Construction is currently taking place on both the eastbound and westbound off-slip roads, within the south side of the roundabout, at the entrance to Upper Studley Farm and south of the roundabout between Hay Lane and Swindon Road.

Once complete, the new junction will improve highway access to major new housing developments, reduce congestion and delay at the junction and reduce the likelihood of queuing back onto the M4. Currently 45,000 vehicles use the junction each day, which includes 5,500 vehicles an hour during peak periods.

In the future the junction will support up to 61,000 vehicles per day and 8,500 vehicles per hour at peak times.

Further details about the scheme can be found at: http://www.swindon.gov.uk/junction16 
RELATED CONTENT
Rodbourne Road Roadworks
Rodbourne Road Roadworks Bus lanes now open to help motorists & local trade as pedestrians follow in the footsteps old GWR workers - NOW REOPENED
More26 April 2016
Swindon: Then and Now
Swindon: Then and Now An exhibition at STEAM celebrating 175 years since the birth of Swindon as a railway town - 23 APRIL - 31 MARCH
More
30 Years On
30 Years On Large crowd braves the rain to hear the Hooter sound again. Swindon Works closed 26 March 1986 - WATCH VIDEO
More26 March 2016
Bruce Almighty!
Bruce Almighty! TALKING POINT: It's the new 'roundabout' we've waited months for but is it a disaster zone or great traffic control? HAVE YOUR SAY
More09 March 2016
Stratton Railway Bridge Re-opens!
Stratton Railway Bridge Re-opens! Motorists breathe sigh of relief as Stratton Railway Bridge re-opens after nearly 4 months - SEE PICTURES
More29 February 2016
Avoid Bruce St Bridges TODAY (and the next 2 weeks probably)
Avoid Bruce St Bridges TODAY (and the next 2 weeks probably) TRAFFIC: Major disruption expected as new junction is completed...
More25 November 2015
myswindonweb
Deacons
Janet's Puppy School
Chelworth Windows and Conservatories, Swindon, Wiltshire
Toomers